Porreres wastewater treatment plant has been extended in response to a need pending since 2007: to adapt the facilities to population growth, the Balearic Water Plan and the process of separating the networks. The works sought to improve wastewater treatment and prevent rainwater from entering the system.
Project to extend and remodel the Porreres WTP
Mallorca (Porreres)
Govern de les Illes Balears
Agència Balear de l'Aigua i la Qualitat Ambiental (ABAQUA)
ITS2016-016
2.662.000 €
2.662.000 €
2.317.683 €
2016
Executed
Environment
Executed: 87.07%
10.02.2022
The project will expand the network of pumping stations, collectors and outfalls to improve wastewater treatment in Andratx, Port d’Andratx and s’Arracó
Mallorca
2.009.485 €
Status: In execution
The purchase of this property in a key natural setting will connect trails and strengthen environmental management
Mallorca
6.770.000 €
Status: Executed
The municipality is taking action on urban tanks to reduce water losses and ensure supply
Mallorca
206.348 €
Status: Executed